← BAC-laskuri
Budget at Completion Calculator · April 2026 · 5 min read · Printable

PMP Earned Value Cheat Sheet

If you are studying for the PMP exam, you need to memorize these formulas. This cheat sheet is designed to be printed and kept as a quick reference guide during study sessions.

1. Complete Terminology (Including Old Names)

AbbrOld NameFull NameDefinition
BACBudget at CompletionOriginal project budget (fixed at baseline).
PVBCWSPlanned ValueBudgeted value of the work planned to be done.
EVBCWPEarned ValueBudgeted value of the work actually completed.
ACACWPActual CostActual money spent to complete the work.

2. All EVM Formulas & Memory Tricks

MetricFormulaWhat it means
Cost Variance (CV)EV - ACUnder or over budget? ($)
Trick: EV always comes first in variance formulas!
Schedule Variance (SV)EV - PVAhead or behind schedule? ($)
Trick: SV uses PV because Schedule = Planned.
Cost Performance Index (CPI)EV / ACCost efficiency of resources used.
Trick: EV is always on top for index formulas!
Schedule Performance Index (SPI)EV / PVEfficiency of time used.
Trick: above 1 is good, below 1 is bad.
EAC (typical performance)BAC / CPIMost common EAC formula. Past performance continues.
Trick: original budget divided by current efficiency.
EAC (one-time variance)AC + (BAC - EV)Future work will proceed at the planned rate.
EAC (schedule pressure)AC + [(BAC-EV)/(CPI×SPI)]Use when a firm deadline forces additional costs.
Estimate to Complete (ETC)EAC - ACHow much more money is needed to finish?
Variance at Completion (VAC)BAC - EACWill we finish under or over budget?
Trick: Baseline minus Forecast.
To-Complete Perf. Index (TCPI)(BAC-EV)/(BAC-AC)Efficiency needed to hit the original BAC.

3. Interpretation Quick-Reference

CPI & SPI

  • Above 1.0: Good (under budget / ahead)
  • 1.0: Exactly on target
  • 0.9–0.99: Warning (slight overrun)
  • Below 0.9: Bad (significant problem)

TCPI

  • Below 1.0: Good (easily achievable)
  • 1.0–1.1: Warning (challenging)
  • Above 1.1: Bad (unlikely without change)

Variances (CV, SV, VAC)

  • Positive (+): Favorable
  • Zero (0): On target
  • Negative (−): Unfavorable

4. PMP Exam-Specific Tips

Practice These Formulas With Interactive Questions

Use our free calculator and built-in PMP quiz to test your knowledge with PMBOK-based scenario questions.

→ Open PMP Practice Quiz