Ipasok ang BAC, PV, EV at AC upang agad na makalkula ang lahat ng sukatan ng EVM — CPI, SPI, EAC, ETC, VAC, TCPI at iba pa. Pinapagana ng mga formula ng PMBOK 6th Edition.
Ilagay ang mga indibidwal na gastos upang makalkula ang iyong Budget at Completion
Subukan ang iyong kaalaman sa EVM gamit ang mga tanong batay sa PMBOK
| Abbr | Old Name | Full Name | Formula | Meaning |
|---|---|---|---|---|
| BAC | — | Budget at Completion | Sum of budgets | Fixed baseline |
| PV | BCWS | Planned Value | %plan × BAC | Scheduled work value |
| EV | BCWP | Earned Value | %done × BAC | Work value done |
| AC | ACWP | Actual Cost | — | Money spent |
| CPI | — | Cost Performance Index | EV / AC | >1 = under budget |
| SPI | — | Schedule Performance Index | EV / PV | >1 = ahead of schedule |
| CV | — | Cost Variance | EV − AC | Neg = over budget |
| SV | — | Schedule Variance | EV − PV | Neg = behind schedule |
| EAC | — | Estimate at Completion | BAC / CPI | Projected final cost |
| ETC | — | Estimate to Complete | EAC − AC | Remaining cost |
| VAC | — | Variance at Completion | BAC − EAC | Budget surplus/deficit |
| TCPI | — | To-Complete Perf. Index | (BAC−EV)/(BAC−AC) | Needed efficiency |
Ang Budget at Completion (BAC) ay ang kabuuang naaprubahang badyet para sa lahat ng trabaho sa proyekto.
Gamitin ang calculator na ito sa pamamagitan ng pagbuo ng BAC sa BAC Builder, pagkatapos ay ilagay ang PV, EV at AC.
Gamitin ang tab ng BAC Builder: ilagay ang mga kategorya ng gastos at agad na kalkulahin ang lahat ng EVM metrics.
Tinutukoy ng PMBOK 6th Edition ang apat na EAC formula na ipinapakita dito.
Sinusubok ng pagsusulit ng PMP ang lahat ng mga EVM formula ng PMBOK 6th Edition.
CPI = EV ÷ AC. Ito ang pinakamahalagang sukatan sa Earned Value Management.