Syötä BAC, PV, EV ja AC laskeaksesi heti kaikki EVM-mittarit — CPI, SPI, EAC, ETC, VAC, TCPI ja muut. Perustuu PMBOK 6. painoksen kaavoihin.
Syötä yksittäiset kustannuserät laskeaksesi Budget at Completion
Testaa EVM-tietosi PMBOK-pohjaisilla kysymyksillä
| Abbr | Old Name | Full Name | Formula | Meaning |
|---|---|---|---|---|
| BAC | — | Budget at Completion | Sum of budgets | Fixed baseline |
| PV | BCWS | Planned Value | %plan × BAC | Scheduled work value |
| EV | BCWP | Earned Value | %done × BAC | Work value done |
| AC | ACWP | Actual Cost | — | Money spent |
| CPI | — | Cost Performance Index | EV / AC | >1 = under budget |
| SPI | — | Schedule Performance Index | EV / PV | >1 = ahead of schedule |
| CV | — | Cost Variance | EV − AC | Neg = over budget |
| SV | — | Schedule Variance | EV − PV | Neg = behind schedule |
| EAC | — | Estimate at Completion | BAC / CPI | Projected final cost |
| ETC | — | Estimate to Complete | EAC − AC | Remaining cost |
| VAC | — | Variance at Completion | BAC − EAC | Budget surplus/deficit |
| TCPI | — | To-Complete Perf. Index | (BAC−EV)/(BAC−AC) | Needed efficiency |
Budget at Completion (BAC) on projektin kaikkien töiden hyväksytty kokonaisbudjetti.
Käytä tätä laskuria rakentamalla BAC alhaalta ylös ja syötä sitten PV, EV ja AC EVM-mittareiden laskemiseksi.
Syötä BAC-rakentajaan jokainen kustannusluokka. Laske sitten CPI, SPI ja EAC nopeasti.
PMBOK 6. painos määrittelee neljä eri EAC-kaavaa projektin tilanteen mukaan.
PMP-koe testaa kaikki EVM-kaavat. Käytä PMP-harjoitteluvälilehteä.
CPI = EV ÷ AC. Se on EVM:n tärkein yksittäinen mittari, joka kertoo kustannustehokkuuden.