輸入BAC,PV,EV和AC即可立即計算所有EVM指標 — CPI,SPI,EAC,ETC,VAC,TCPI等。基於PMBOK第6版公式。
輸入各個成本項目以計算您的Budget at Completion
透過基於PMBOK的問題測試您的實獲值管理知識
| Abbr | Old Name | Full Name | Formula | Meaning |
|---|---|---|---|---|
| BAC | — | Budget at Completion | Sum of budgets | Fixed baseline |
| PV | BCWS | Planned Value | %plan × BAC | Scheduled work value |
| EV | BCWP | Earned Value | %done × BAC | Work value done |
| AC | ACWP | Actual Cost | — | Money spent |
| CPI | — | Cost Performance Index | EV / AC | >1 = under budget |
| SPI | — | Schedule Performance Index | EV / PV | >1 = ahead of schedule |
| CV | — | Cost Variance | EV − AC | Neg = over budget |
| SV | — | Schedule Variance | EV − PV | Neg = behind schedule |
| EAC | — | Estimate at Completion | BAC / CPI | Projected final cost |
| ETC | — | Estimate to Complete | EAC − AC | Remaining cost |
| VAC | — | Variance at Completion | BAC − EAC | Budget surplus/deficit |
| TCPI | — | To-Complete Perf. Index | (BAC−EV)/(BAC−AC) | Needed efficiency |
Budget at Completion (BAC)是為所有專案工作批准的總預算,在執行開始前作為基準建立。它是衡量整個專案生命週期內Earned Value (EV)和Actual Cost (AC)的固定財務基準。根據PMBOK第6版第263頁,BAC等於將要執行的工作的所有預算之和。
使用這個免費的budget at completion計算機,首先在BAC建構器標籤中根據個別成本項目由下而上建立您的BAC,然後輸入您的PV,EV和AC即可立即計算所有EVM指標。
要計算budget at completion,請使用BAC建構器標籤:輸入每個成本類別(人工、材料、設備、分包商、管理費、應急儲備),工具會自動將它們彙總為您的BAC。然後輸入PV(planned value),EV(完成百分比或金額),以及AC(actual cost),立即計算CPI,SPI,全部四個EAC公式,ETC,VAC和TCPI。免註冊,100%客戶端運行。
PMBOK第6版定義了四個Estimate at Completion (EAC)公式。根據您的專案情況進行選擇:當過去的績效持續時 EAC=BAC/CPI;對於一次性偏差 EAC=AC+(BAC-EV);當受到持續的成本影響時 EAC=AC+(BAC-EV)/CPI;當進度壓力增加成本時 EAC=AC+(BAC-EV)/(CPI×SPI)。該EAC計算機同時顯示所有四個公式。
PMP®考試測試PMBOK第6版中的所有實獲值管理公式。使用PMP練習標籤進行互動式測驗,並參考完整的EVM術語表——包括仍然在考試中出現的舊術語BCWP,BCWS和ACWP。
Cost Performance Index (CPI) = EV ÷ AC。它是實獲值管理中最重要的單一指標——它告訴您專案的預算支出效率如何。CPI高於1.0意味著低於預算(每花費$1,完成的工作超過$1)。CPI低於1.0意味著超出預算。研究表明,一旦CPI降至0.9以下,在達到20%的完成率之後很少能恢復——因此早期測量至關重要。