Unesite BAC, PV, EV i AC kako biste trenutno izračunali sve EVM metrike — CPI, SPI, EAC, ETC, VAC, TCPI i više. Temeljeno na formulama PMBOK 6. izdanja.
Unesite pojedinačne stavke troškova kako biste izračunali BAC
Testirajte svoje znanje o EVM-u pitanjima temeljenim na PMBOK-u
| Abbr | Old Name | Full Name | Formula | Meaning |
|---|---|---|---|---|
| BAC | — | Budget at Completion | Sum of budgets | Fixed baseline |
| PV | BCWS | Planned Value | %plan × BAC | Scheduled work value |
| EV | BCWP | Earned Value | %done × BAC | Work value done |
| AC | ACWP | Actual Cost | — | Money spent |
| CPI | — | Cost Performance Index | EV / AC | >1 = under budget |
| SPI | — | Schedule Performance Index | EV / PV | >1 = ahead of schedule |
| CV | — | Cost Variance | EV − AC | Neg = over budget |
| SV | — | Schedule Variance | EV − PV | Neg = behind schedule |
| EAC | — | Estimate at Completion | BAC / CPI | Projected final cost |
| ETC | — | Estimate to Complete | EAC − AC | Remaining cost |
| VAC | — | Variance at Completion | BAC − EAC | Budget surplus/deficit |
| TCPI | — | To-Complete Perf. Index | (BAC−EV)/(BAC−AC) | Needed efficiency |
BAC je ukupan odobreni budžet za sav rad, uspostavljen prije izvršenja. Prema PMBOK 6. izdanju, BAC je jednak zbroju svih budžeta.
Koristite ovaj kalkulator izgradnjom BAC-a iz pojedinačnih stavki na kartici BAC Graditelj, a zatim unesite PV, EV i AC za izračun EVM metrika.
Za izračun BAC-a, koristite karticu BAC Graditelj: unesite svaku kategoriju troškova i alat će ih zbrojiti. Zatim unesite PV, EV i AC.
PMBOK 6. izdanje definira četiri EAC formule. Odaberite na temelju vaše situacije: EAC=BAC/CPI; EAC=AC+(BAC-EV); EAC=AC+(BAC-EV)/CPI; EAC=AC+(BAC-EV)/(CPI×SPI).
PMP® ispit testira sve EVM formule iz PMBOK 6. izdanja. Koristite PMP karticu za kviz pitanja i referencu.
CPI = EV ÷ AC. Najvažnija metrika u EVM-u — govori vam koliko se učinkovito troši vaš budžet.